How to Obtain a Temporary LESCO Electricity Connection

Temporary electricity connections are essential for short-term needs, such as events, construction projects, or industrial purposes. This guide outlines the process to acquire a temporary LESCO connection, which remains valid for six months. Extensions, if required, can be requested by submitting a written application to WAPDA along with a demand notice fee.

Applying for a Residential Temporary LESCO Connection

For residential purposes, such as construction of a new house, follow these steps to apply online for a temporary LESCO connection:

Step-by-Step Application Process

  1. Access the Application Form
  • Visit LESCO’s official temporary connection application page and click “Apply Here.”
  1. Provide Details
  • Select “LESCO” as the electricity provider.
  • Identify your respective subdivision (e.g., Lahore Cantt).
  • Select the applicable category type (e.g., up to 15KW).
  • Enter a neighbour’s meter reference number.
  1. Enter Personal Information
  •  
  • Fill in your name, CNIC details, and contact information.
  • Indicate the total number of meters already registered under your name.
  1. Upload Required Documents
  •  
  • Property ownership document (copy).
  • Attested CNIC copies of the applicant and a witness.
  • Copy of the neighbour’s electricity bill.
  • Wiring contractor’s test report.

After Online Submission

  1. Print your application and attach all uploaded documents.
  2. Submit the completed file at your relevant LESCO subdivision office.
  3. LESCO will verify your application and conduct an on-site survey.
  4. If approved, a demand notice will be issued. Pay the associated fee at the designated bank, attaching your test report.

Track your application status on LESCO’s official website.

Applying for a Temporary Industrial LESCO Connection

For industrial purposes, applications for temporary connections are facilitated by the Punjab Industrial Estate Development and Management Company (PIEDMC). Follow these steps:

Application Process

  1. Download the Application Form
  • Obtain the industrial connection form from PIEDMC’s official website.
  1. Complete the Form
  • Fill in and sign the form. Include a cover letter and the required documents.
  • Required documents include:
  • CNIC copies (for both owner and witness).
  • Allotment and possession letter copies.
  1. Application Submission
  • Submit the completed form and documents to the Electrical Department at PIEDMC.

Once the site inspection is conducted and approved, a demand notice will be issued. After payment of the related charges, the temporary industrial connection will be arranged.